Pass Guaranteed 2025 Medical Professional Newest CCM Latest Exam Papers
If you want to sharpen your skills, and get the Certified Case Manager Certification Exam (CCM) (CCM) certification done within the target period, it is important to get the best Certified Case Manager Certification Exam (CCM) (CCM) exam questions. You must try the TestPassKing Certified Case Manager Certification Exam (CCM) (CCM) practice exam that will help you get the Medical Professional CCM Certification. TestPassKing hires the top industry experts to draft the Certified Case Manager Certification Exam (CCM) (CCM) exam dumps and help the candidates to clear their Certified Case Manager Certification Exam (CCM) (CCM) exam easily. TestPassKing plays a vital role in their journey to get the CCM certification.
Full refund is available if you fail to pass the exam in your first attempt after buying CCM exam bootcamp from us, and we will refund your money, In addition, CCM exam dumps contain both questions and answers, and it’s convenient for you to check the answers after practicing. CCM exam botcamp cover most of the knowledge points of the exam, and you can master the major knowledge points as well as improve your professional ability in the process of training. We have online and offline chat service for CCM Exam Dumps, and if you have any questions, you can consult us.
Updated CCM Demo & Exam CCM Fees
With the unemployment rising, large numbers of people are forced to live their job. It is hard to find a high salary job than before. Many people are immersed in updating their knowledge. So people are keen on taking part in the CCM exam. As you know, the competition between candidates is fierce. If you want to win out, you must master the knowledge excellently. And our CCM study questions are the exact tool to get what you want. Just let our CCM learning guide lead you to success!
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions (Q36-Q41):
NEW QUESTION # 36
Which of the following statements are not correct?
Choose all of the correct answers (multiple possibilities).
Answer: A,D
Explanation:
In FIDIC contracts (2017 editions), meetings such as progress or management meetings are key tools for communication and coordination among parties. The contract provisions and practical use reflect flexibility regarding who can request or call for such meetings.
* Option Ais correct: Both the Contractor and the Engineer can request or call meetings as needed to discuss project progress, issues, or coordination. This promotes proactive communication.
* Option Bisincorrect(and therefore included in the answer): It is not only the Engineer who can call meetings. The Contractor can also request meetings.
* Option Cis generally correct: Subcontractors may attend meetings only with the Engineer's approval or if invited. This controls confidentiality and relevance of discussions.
* Option Disincorrect: Only the Employer calling meetings is not correct. The Employer may do so but is not the only party authorized.
* Option Eis correct: The Engineer typically keeps records (minutes) of progress meetings to document discussions, decisions, and agreed actions. This is essential for contract administration.
Hence, theincorrectstatements areBandD.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 4.28 - Progress Reports and Meetings FIDIC Yellow Book 2017 Edition, similar clauses on meetings and communication FIDIC Contract Manager Study Guide, Module on Communication and Reporting
NEW QUESTION # 37
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?
Answer: A
Explanation:
This statement is true. The Silver Book (EPC/Turnkey contracts) usually involves lump-sum payment, but if part payment is based on quantity or work done, this must be explicitly provided for in the Particular Conditions to avoid ambiguity.
Such provisions ensure clarity on payment terms in line with project specifics.
References:
FIDIC Silver Book 1999 & 2017 Editions, Sub-Clause 14 - Payment Provisions FIDIC Contract Manager Study Guide, Module on Payment Procedures
NEW QUESTION # 38
During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers on the excavator shouts out to the supervisor of the Contractor it has discovered something on the Site. The supervisor inspects the finding and concludes this is possibly an ancient treasure in a wooden box. The supervisor sees some golden coins through the cracked lid of the box.
The supervisor immediately stops the execution of the Works, sends the workers away and blocks access to the Site for all persons. Given the sensitive nature of the findings, the supervisor informs you as Engineer.
How do you react?
Answer: B
Explanation:
Comprehensive and Detailed Explanation:
Under FIDIC Yellow Book 1999, Sub-Clause 4.24 ("Unforeseeable Physical Conditions") deals with unexpected discoveries such as archaeological finds. The Engineer's role includes ensuring site safety, notifying the Employer and relevant authorities, and managing the implications through variations.
Option B reflects best practice: securing the site, appointing guards, notifying Employer and authorities, and requesting a formal Variation Notice to cover costs and entitlement to extension of time.
Options A and D are unsafe or legally risky actions that could damage the find and breach legal obligations.
Option C delays the necessary immediate protective actions.
References:
FIDIC Yellow Book 1999 Edition, Sub-Clause 4.24 - Unforeseeable Physical Conditions FIDIC Contract Manager Study Guide, Module on Claims and Variation Management
NEW QUESTION # 39
Giving "Notice" .... [2017 edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Answer: C,D
Explanation:
Option B is correct: Notices are compulsory when required and must reference the relevant Sub-Clause to be valid.
Option D is correct: Notices are formal written communications and must comply with the contract's prescribed procedures.
Option A is incorrect; notices are often mandatory, not merely recommended.
Option C is incorrect; notices are obligations for all Contract Participants, not just the Engineer.
References:
FIDIC Red, Yellow, Silver Books 2017 Edition, Sub-Clause 1.3 - Communications FIDIC Contract Manager Study Guide, Module on Notices and Communication
NEW QUESTION # 40
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?
Answer: B
Explanation:
Comprehensive and Detailed Explanation:
The Contractor may submit Value Engineering proposals to improve efficiency or reduce costs; however, it is not an absolute contractual obligation to submit such proposals. Also, the preparation of these proposals is generally at the Contractor's own cost initially. If the proposal is accepted and results in a Variation, then adjustments to the Contract Price may occur, potentially reimbursing the Contractor.
Thus, both statements are false.
References:
FIDIC Red, Yellow, Silver Books 1999 & 2017 Editions, Sub-Clause 13.1 - Value Engineering FIDIC Contract Manager Study Guide, Module on Variations and Value Engineering
NEW QUESTION # 41
......
Passing the CCM exam with least time while achieving aims effortlessly is like a huge dream for some exam candidates. Actually, it is possible with our proper CCM learning materials. To discern what ways are favorable for you to practice and what is essential for exam syllabus, our experts made great contributions to them. All CCM Practice Engine is highly interrelated with the exam. You will figure out this is great opportunity for you. Furthermore, our CCM training quiz is compiled by professional team with positive influence and reasonable price
Updated CCM Demo: https://www.testpassking.com/CCM-exam-testking-pass.html
Medical Professional CCM Latest Exam Papers SUPPORT BEYOND THE PURCHASE, Also, our CCM practice exam has timed mock test, which enables you to manage time accordingly and it's real exam simulation helps you to pass CCM exam on the first try, Medical Professional CCM Latest Exam Papers We also estimate the following trend of exam questions may appear in the next exam according to syllabus, All CCM guide exam can cater to each type of exam candidates’ preferences.
It is very easy for a computer to win some games, Uncertainty manifests itself when the unplanned happens, SUPPORT BEYOND THE PURCHASE, Also, our CCM Practice Exam has timed mock test, which enables you to manage time accordingly and it's real exam simulation helps you to pass CCM exam on the first try.
Quiz Medical Professional - CCM –Reliable Latest Exam Papers
We also estimate the following trend of exam questions may appear in the next exam according to syllabus, All CCM guide exam can cater to each type of exam candidates’ preferences.
Also our answers and explanations of CCM practice test are easy to practice and understand.