Latest PSP Exam Answers - PSP Reliable Braindumps Pdf
P.S. Free 2025 ASIS PSP dumps are available on Google Drive shared by BraindumpsPrep: https://drive.google.com/open?id=16tlsVQmxQPBT3n3jpF8sv-BdMdZfvQR9
Our PSP exam questions are totally revised and updated according to the changes in the syllabus and the latest developments in theory and practice. We carefully prepare the PSP test guide for the purpose of providing high-quality products. All the revision and updating of products can graduate the accurate information about the PSP Guide Torrent you will get, let the large majority of student be easy to master and simplify the content of important information. Our product PSP test guide delivers more important information with fewer questions and answers.
ASIS PSP Certification Exam is designed to assess the competencies of security professionals in physical security management. PSP exam consists of 125 multiple-choice questions, which are based on six domains of physical security management. The six domains include physical security assessment, application, design, implementation, operations, and maintenance.
Latest PSP Exam Answers has 100% pass rate, ASIS Physical Security Professional Exam
I would like to bring to you kind attention that our latest ASIS PSP study guide is produced. These exam materials are high passing rate. We are sure that PSP study guide will be the best assist for your coming exam. We guarantee "No Pass Full Refund". If you feel depressed about your past failure and eager to look for Valid PSP Study Guide, I advise you to reply to our exam materials as 100% passing without any doubt. Thousands of candidates' choice for our PSP study guide will be your wise decision.
ASIS Physical Security Professional Exam Sample Questions (Q150-Q155):
NEW QUESTION # 150
What is the free float for Activity F?
Answer: C
Explanation:
Understand Free Float:Free float is the time an activity can be delayed without delaying the start of its immediate successor.
Review Activity F in the Diagram:
* Activity F has a successor that starts later, providing room for 2 months of free float.
Cross-Verification:
* Option A: Incorrect. Overestimates the float.
* Option B: Incorrect. No float is incorrect for F.
* Option C: Incorrect. 1 month is insufficient.
* Option D: Correct. Matches the calculated free float for Activity F.
NEW QUESTION # 151
When resource leveling craft labor for a critical path schedule, the scheduler
Answer: D
Explanation:
Resource Leveling:
* Resource leveling adjusts start and finish dates of activities to resolve resource conflicts or constraints, balancing availability and demand.
* In construction projects, breaks in continuity of work for subcontractors can result in increased costs due to remobilization and demobilization.
PSP Study Guide References:
* The PSP guide explains that resource leveling must be carefully analyzed to avoid disruptions in work continuity.
Conclusion: The correct answer is A, as the scheduler must account for potential cost implications of resource leveling on subcontractors.
NEW QUESTION # 152
Each of the following accurately describes total float in a schedule EXCEPT:
Answer: B
Explanation:
Total float measures the flexibility in an activity's timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project's overall completion date or the completion date of any of its successors.
* Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.
* Option C describes free float, not total float, and thus is incorrect.
NEW QUESTION # 153
You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor has included codes for each activity that identify {1) the category of work and (2) the trade
/subcontract performing the work. What can this code information be used for?
Answer: D
NEW QUESTION # 154
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
Answer: D
Explanation:
Calculation of Total Lifts Required:
* 3 column pours = 28×3=8428 imes 3 = 8428×3=84.
* Additional lifts = 150150150.
* Total lifts = 84+150=23484 + 150 = 23484+150=234.
Lifts Per Day with One Crane:
* 1 crane performs 30 lifts per day.
Required Duration:
* Minimum planned working duration = #234÷30#=18lceil 234 div 30 ceil = 18#234÷30#=18.
Verification with PSP Guidelines:Aligning workload with equipment capacity ensures practical schedule planning (Ref: PSP Study Guide, Chapter 2B: Workload Balancing).
NEW QUESTION # 155
......
There is no need to worry about virus on buying electronic products. For BraindumpsPrep have created an absolutely safe environment and our exam question are free of virus attack. We make endless efforts to assess and evaluate our PSP exam question’ reliability for a long time and put forward a guaranteed purchasing scheme. If there is any doubt about it, professional personnel will handle this at first time, and you can also have their remotely online guidance to install and use our PSP Test Torrent.
PSP Reliable Braindumps Pdf: https://www.briandumpsprep.com/PSP-prep-exam-braindumps.html
DOWNLOAD the newest BraindumpsPrep PSP PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=16tlsVQmxQPBT3n3jpF8sv-BdMdZfvQR9